As authorities begin the construction of the Dahisar-Andheri Metro line, traffic diversions will come into place on the Western Express Highway; mid-day gives you a lowdown of the blocked lanes and routes to beware of
Western Express Highway
ADVERTISEMENT
Section 1
Metro mall to Devipada Temple
Section 2
Saibaba temple at Pathanwadi to Pushpa park
Section 3
Hub mall to Aarey Flyover
Plan of action
>> The MMRDA will first identify the various utilities and thereafter begin the excavation work
>> Service roads and slip roads will be used for barricading and excavation work
>> No parking will be allowed on such roads