MMRDA to widen Eastern Express Highway
By: 

 

The work will start within a monthThe MMRDA, under the Mumbai Urban Infrastructure Project (MUTP) will soon begin work on widening the Eastern Express Highway, from Sion to Mulund.

The project will be executed in the following phases: Sion flyover to Ghatkopar, Ghatkopar to Godrej Company Gate (north), Godrej Company Gate (north) to Juhu Vile Parle Link Road Junction (JVLR), JVLR Junction to Ghatkopar-Mankhurd Link Road Junction and from GMLR Junction to Mulund check naka.

An officer of MMRDA says, The work on the project will start in a month, as tenders have already been invited. The work has been divided into different sections and is likely to start simultaneously on all the sections. depending on the nature of work involved and traffic diversions, the time taken may vary. While some structures may take up to 12 months, some may take up to two years.

priya@mid-day.com

The details of the phases

Work

Estimated Cost

Period of completion

Sion flyover to Ghatkopar
(km 584.35 to 579.00)

Rs 3,071 lakh

15 months

Ghatkopar to Godrej Company Gate (north)
(km 579.00 to 575.40)

Rs 2,782 lakh

15 months

Godrej Co Gate (north) to JVLR Junction
(km 575.40 to 572.60)

Rs 1,810 lakh

12 months

JVLR Junction to GMLR Junction (km 572.60 to 568.70)

Rs 2, 889 lakh

15 months

GMLR Junction to Mulund check naka (Km 568.70 to 566.00)

Rs 1, 680 lakh

12 months