CR maintains overhead wires, removes muck during mega block

Updated on: 21 July,2020 08:20 AM IST  |  Mumbai
Rajendra B Aklekar |

The works were undertaken by Central Railway Mumbai divisions corona warriors during maintenance work on the mainline between Thane and Kalyan fast lines and CSMT-Chunabhatti harbour lines

CR maintains overhead wires, removes muck during mega block

Central Railway Mumbai Division's corona warriors working on the contact wire over bridge

During Sunday's mega block, the Central Railway team worked on the renewal of 2.6km of rail track by road-rail vehicle, overhauling of 1.3 km of overhead wires, and picked up over 2,000 bags of muck and garbage. These works were undertaken by Central Railway Mumbai division's corona warriors during the maintenance work on the mainline between Thane and Kalyan fast lines and CSMT-Chunabhatti harbour lines on July 19.


CR-Muck-Removal
Central Railway's team picked up over 2,000 bags of muck and garbage


Engineering


Speaking to mid-day, Central Railway's chief public relations officer Shivaji Sutar said the CR railway team took up the task of renewal of 2.6 fast track km near Parsik Tunnel on fast lines. The challenging work of 28 sleepers over crossings was hauled and replaced by a newly innovated Rail Road Vehicle. Ballast tamping of 1.4 km plain track was also carried out. Alumino-thermic welding at 16 places was also done for joining rails. In addition to this, six wagons of muck were removed by JCB machine, and 2,000 muck bags were loaded manually on harbour line by engineering warriors.

CR-Tower-Wagon
The Central Railway Mumbai division staff work on the tower wagon during Sunday's mega block

Overhead Equipment Works

Sutar added that annual overhauling of 1.3 km length of overhead equipment was carried out by three tower wagons, besides carrying out other electrical maintenance works.

CR-Creek-Bridge
The Central Railway team carried out Ballast tamping of 1.4 km plain track

Signaling and Telecom Works

Signaling works done this week include "duo-matic machine packing", replacement of track lead wires, and 2 sets of points and disconnection and reconnection of axle counters on a length of 2.6 km track in tune with engineering works at Diva and Dativali chord line, Sutar added.

Catch up on all the latest Mumbai news, crime news, current affairs, and a complete guide from food to things to do and events across Mumbai. Also download the new mid-day Android and iOS apps to get latest updates.

Mid-Day is now on Telegram. Click here to join our channel (@middayinfomedialtd) and stay updated with the latest news

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!


Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK