Ghat section on Pune-Mumbai E-way may not be part of NH4

Updated on: 28 November,2012 07:11 AM IST  | 
Sukirt D Gumaste |

According to a senior MSRDC official, by separating the section between Khalapur and Khopoli exit point from old Pune-Mumbai Highway, they'll be able to reduce traffic on the Expressway by about 50 per cent

Ghat section on Pune-Mumbai E-way may not be part of NH4

As per the comprehensive proposal prepared by the Maharashtra State Road Development Corporation (MSRDC) for the Pune-Mumbai Expressway expansion project, the ghat section between Khalapur and Khopoli exit point will be separated from NH4 (old Pune-Mumbai Highway).



Boon for motorists: The Maharashtra State Road Development Corporation even wants to increase the number of lanes on the Pune-Mumbai Expressway from six to eight. File pic


The proposal will be presented before the MSRDC board members, and if approved, will be forwarded to the state government. According to the proposal, the E-way will be expanded in the three phases. In first phase, a tunnel will be constructed from Khalapur to Khopoli exit point.

“As the ghat section is common to both the highways, it witnesses major traffic jams. Besides, heavy vehicles coming from both the highways occupy major portion of the road during the night. Hence, if the common section is separated then we’ll be able to divert almost 50 per cent of the traffic to the old highway,” a senior MSRDC official said.

He added that during the construction of the E-way, the road development corporation had demanded construction of a separate Expressway from NH4. “However, the transport department didn’t give the permission. Thus, the common ghat section became root cause of the major problems that people face on E-way,” he said.

The official also informed that the project would be implanted under Build Operate Transfer (BOT) basis, and hence budget won’t be the problem. Even the toll charges will not increase. “After getting all the approvals, the construction would require a minimum four years,” he said.

He added that in the second phase of expansion, the lanes on the E-way would be increased from six to eight. u00a0He said, “An additional lane on both sides of the Expressway will be constructed at the entire stretch. While in the third phase, we plan to add two more lanes to the existing old Pune-Mumbai Highway.”u00a0


"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!


Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK