Home / Mumbai / Mumbai News / Article / Road concretisation: Here’s why Mumbai has road rage!

Road concretisation: Here’s why Mumbai has road rage!

BMC announced a May 31 deadline for completing concreting work of all dug up roads, yet a test drive by mid-day just over a week before deadline reveals that it would take nothing short of a miracle to complete work by the month-end

Listen to this article :
Pics/Ashish Raje and Nimesh Dave

Pics/Ashish Raje and Nimesh Dave

Following the recent heavy showers and a weather alert issued by the India Meteorological Department (IMD), Mumbaikars are increasingly anxious about the state of city roads. The BMC had set a deadline of May 31 to complete all work on roads already dug up for cement concreting (CC) across the city. However, a ground visit by mid-day to several locations revealed that work remains incomplete in many areas, raising concerns among residents and commuters — especially with the monsoon just around the corner.

Additional Municipal Commissioner  Abhijit BangarAdditional Municipal Commissioner Abhijit Bangar

Exhibition Ad Banner
Exhibition Ad Banner

How do you like the new new mid-day.com experience? Share your feedback and help us improve.

Read Next Story
Mumbai Diary: Saturday Dossier

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement