In Photos: Commuters cross tracks as Mahim FOB undergoes urgent repairs

Updated On: 22 April, 2025 02:00 PM IST | Anushree Gaikwad

Due to urgent repair work currently underway on the foot over bridge (FOB) at Mahim station in Mumbai, several commuters were seen crossing the railway tracks to get to the other side. (Pics/ Atul Kamble)

01
In light of the ongoing urgent repair work on the south-end foot over bridge (FOB) at Mahim station, authorities have taken steps to ensure minimal disruption to commuter movement. Pic/Atul Kamble
In light of the ongoing urgent repair work on the south-end foot over bridge (FOB) at Mahim station, authorities have taken steps to ensure minimal disruption to commuter movement. Pic/Atul Kamble
02
To ensure commuter convenience, two alternate foot overbridges located at the north end of Mahim station remain accessible, allowing passengers to move between the station and both the eastern and western sides

To ensure commuter convenience, two alternate foot overbridges located at the north end of Mahim station remain accessible, allowing passengers to move between the station and both the eastern and western sides

03
The Western Railway has initiated urgent repair work on the Mahim South foot overbridge, which falls under the jurisdiction of the Brihanmumbai Municipal Corporation (BMC)

The Western Railway has initiated urgent repair work on the Mahim South foot overbridge, which falls under the jurisdiction of the Brihanmumbai Municipal Corporation (BMC)

04
The decision was made following the discovery of cracked precast RCC slabs and severely corroded, perforated supporting beams

The decision was made following the discovery of cracked precast RCC slabs and severely corroded, perforated supporting beams

05
The repair work commenced on April 16 and is expected to be completed by April 30

The repair work commenced on April 16 and is expected to be completed by April 30

06
The bridge spans a total length of 40 meters and a width of 4 meters

The bridge spans a total length of 40 meters and a width of 4 meters

07
 So far, the damaged precast RCC slabs have been dismantled

 So far, the damaged precast RCC slabs have been dismantled

08
 20 meters of corroded supporting beams have been replaced

 20 meters of corroded supporting beams have been replaced

09
The laying of chequered plates is currently in progress

The laying of chequered plates is currently in progress