Mumbai Metro Line 4 slab collapse: Project undergoes intensive corridor-wide safety inspection

Updated on: 15 February,2026 09:13 PM IST  |  Mumbai
Ranjeet Jadhav | ranjeet.jadhav@mid-day.com

A slab near pier P196 of the under-construction Mumbai Metro Line 4 had on Saturday collapsed in Mulund area of Mumbai, leaving one person dead and three injured

Mumbai Metro Line 4 slab collapse: Project undergoes intensive corridor-wide safety inspection

The inspection began on February 15, 2026, officials said. Pic/Videograb (Special Arrangement)

Listen to this article
Mumbai Metro Line 4 slab collapse: Project undergoes intensive corridor-wide safety inspection
x
00:00

The Mumbai Metropolitan Region Development Authority (MMRDA) has began intensive corridor-wide safety inspection following the Mumbai Metro Line 4 slab collapse on February 14.

The incident took place on Saturday near pier P196 in Mulund area of Mumbai on the under-construction Metro Line 4, leaving one dead and three others injured.


The MMRDA said that it has formed a special safety team to monitor Wadala-Kasarvadavali metro project and conduct inspections of the works.



Mid-day had earlier in the day reported the launch of a special safety inspection following the Mulund incident. Read more here

The measure aims to ensure public safety, construction quality, and compliance with statutory regulations.

Officials stated that the inspection is a preventive step and does not affect the ongoing investigation into the incident.

A dedicated Special Intensive Safety Inspection Team has been constituted under the leadership of Shri Basavraj M. Bhadragond, Director (Projects), MMRDA.

The team includes Deputy Team Leaders, Project Directors, Safety Heads, Executive Engineers, QA/QC Officers, Design Engineers, and external safety experts from Metro Line-5 and Line-9. External members are tasked with recording observations independently, with their findings forming part of the official record.

Scope of inspection

The inspection is comprehensive and corridor-wide, covering parapets, edge beams, crash barriers, handrails, and attachments, structural elements above live traffic or public areas, precast, cast-in-situ, and interface zones, fixity, anchorage, reinforcement detailing, workmanship and finishing, temporary works, supports, shuttering remnants, and construction debris and barricading, safety nets, exclusion zones, and traffic protection.

Compliance with approved drawings, method statements, and safety protocols

The inspection began on February 15, 2026 and will continue for three to four days, or as directed by the team leader. It combines physical checks with documentary verification, recording observations day-wise on the ongoing Mumbai Metro Line 4 work, and identifying unsafe conditions immediately.

Immediate actions include- 

- Securing, removing, or rectifying unsafe elements without waiting for the final report

- Restricting, regulating, or suspending construction activity at identified unsafe locations

- Full cooperation from contractors, consultants, and supervision staff, including providing site access, drawings, QA/QC records, and inspection reports

- Deliverables and Reporting

The Team Leader will submit- 

- Day-wise inspection notes

- A list of unsafe conditions and immediate actions taken

- A corridor-wide safety and compliance matrix

- A consolidated inspection report detailing findings, corrective and preventive measures, and recommendations on resumption or continuation of works

The report will be submitted to the Competent Authority on priority, officials said.

Commitment to safety

The MMRDA stressed that the step reflects its commitment to public safety, transparency, and adherence to engineering and safety standards.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Did you find this article helpful?

Yes
No

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

mumbai mumbai metro MMRDA mumbai news mulund mumbai transport mumbai metropolitan region development authority thane maharashtra