Chairing a review meeting of infrastructure projects for Mumbai, Thane and Pune here, Fadnavis emphasised the need to use modern technology and to ensure completion of new projects within two to two-and-a-half years
A statement from the CM's Office (CMO) quoted Fadnavis as saying that obstacles faced during the implementation of ongoing projects should be resolved immediately
Senior officials from the administration and representatives of contracting agencies were present at the meeting
Reviewing the Mumbai Metropolitan Region Development Authority's (MMRDA) projects, Fadnavis said Metro Line 2B (DN Nagar to Mandale) with 19 stations should be completed by March 31, 2027, and the Swami Samarth Nagar-Vikhroli line by December 31, 2026
He directed the Urban Development Department to resolve land-related issues at Shyam Nagar station within 15 days