89 pc of land needed for bullet train project acquired: Railway minister tells Lok Sabha

The execution of Mumbai-Ahmedabad high speed rail (MAHSR) has been delayed especially due to delay in land acquisition in the state of Maharashtra and consequent delays in finalisation of contracts as well as adverse impact of Covid-19

Listen to this article :
Railways Minister Ashwini Vaishnaw. File Photo

Railways Minister Ashwini Vaishnaw. File Photo

Approximately 89 per cent of land required for the Mumbai-Ahmedabad bullet train project has been acquired by the Centre, Railways Minister Ashwini Vaishnaw said on Wednesday.

"The execution of Mumbai-Ahmedabad high speed rail (MAHSR) has been delayed especially due to delay in land acquisition in the state of Maharashtra and consequent delays in finalisation of contracts as well as adverse impact of Covid-19," the minister said in his written reply to a question in Lok Sabha.

How do you like the new new mid-day.com experience? Share your feedback and help us improve.

Read Next Story
India's drugs regulator gives nod to phase-3 clinical trial of Covid vaccine Covovax

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement