Get on with the work: MMRDA tells contractor
Updated On: 24 August, 2012 07:42 AM IST | | Ranjeet Jadhav
Three years after the bhoomipujan of the CBM metro line, the contractor has still not begun work, prompting the MMRDA to give it an ultimatum
The Mumbai Metropolitan Region Development Authority (MMRDA) plans to officially inform Mumbai Metro Transport Private Limited (MMTPL) that they should either start work on the Charkop-Bandra-Mankhurd (CBM) metro corridor at the earliest, or make their stand clear on the project. MMTPL, the contractor of the project has not yet started work on the 32 km-long corridor saying that no action can be taken till the issues of setting up a casting yard and car depot are solved.

Nothing to show: The proposed site for the CBM metro rail car shed near Inorbit Mall at Malad. file pic