A significant portion of the new Thane-Diva lines will be commissioned in early January but about 150 hours of rail blocks is required to complete the remaining portion of the project. As per the tentative schedule, six blocks of 18 hours, 24 hours, 36 hours, 14 hours, 8 hours and the final one of 72 hours have been planned.