Delays continue to bog Metro II; contractor could lose contract
Updated On: 13 August, 2012 08:40 PM IST | | Ranjeet Jadhav
The second metro rail corridor contract between Charkop-Bandra-Mankhurd (CBM) has run into trouble due to delays in its construction and the contractor faces the danger of losing his contract for the project.
The Mumbai Metropolitan Region Development Authority (MMRDA) has decided to inform the project’s contractor to start work on the project at the earliest, failing which the company faces the punishment of losing the contract.
“It should be noted that the ground breaking ceremony of the CBM corridor was done three years ago. However the actual work on the line has not started yet as the contractor has told us that they cannot start the work unless the car depot issue and the casting yard issues have been resolved,” an MMRDA source told MiD DAY.