Monsoon Ready? Over half of Mumbai's roads not even 20% repaired
Updated On: 27 March, 2017 08:44 AM IST | | Laxman Singh
Civic data obtained by mid-day shows that of the 558 roads currently dug up, work on 328 has been completed only up to 20%, 113 has reached 50%, and 114 has reached up to 75%


Trust the Brihanmumbai Municipal Corporation (BMC) to have gaping holes in its claims for finishing road repairs. Come monsoon, you can expect another round of bumpy rides on pothole-filled roads, as the civic body is nowhere close to achieving its target for completing repairs on 446 out of 558 roads before the May 31 deadline, as per data accessed by mid-day.