Maharashtra RERA instructs builders to give back interest paid to 15 home-buyers

Authority directs builder to pay interest on amounts already paid for project that has not been completed even though deadline has passed

Listen to this article :

The underconstruction project at Malwani, Malad
The underconstruction project at Malwani, Malad

The Maharashtra Real Estate Regulatory Authority (MahaRERA) is surely and steadily showing its teeth. For the first time, 15 applicants have got relief in a case where they had booked flats in an under-construction project at Malwani, Malad, and the builder failed to meet the deadline. Interestingly, one of the complainants only had a letter of allotment (no agreement was signed), which was accepted by the adjudicating officer at MahaRERA, BD Kapadnis.

Read Next Story
The farm loan behind the Raigad bank furore

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement