Mumbai: CAG validates mid-day report, flays BMC over pumping stations
Updated On: 26 December, 2014 11:41 AM IST | | Sharad Vyas
<p>CAG’s report tabled in Assembly on Wednesday, less than a month after mid-day investigation, has called implementation of pumping stations ‘weak’ and the BMC’s internal controlling mechanisms ‘flawed’</p>

The Lovegrove pumping station
The latest report of the Comptroller and Auditor General (CAG) has validated a mid-day investigation on the mismanagement in construction of pumping stations in Mumbai. The mid-day investigation (‘Contractor’s shoddy job on pumping stations is putting Mumbai at risk’, November 11), exposed the mismanagement in construction of three crucial pumping stations — Lovegrove, Cleveland Bunder and Haji Ali — and had highlighted their poor planning, design and construction.
It had exposed how the projects had countless anomalies and how the contractor sometimes used sub-standard material, often sourced from unlisted suppliers, and violated many tender conditions, thereby not only causing losses to the civic exchequer, but also putting lives at risk.