BMC claims concretisation work completed on 1,385 roads across Mumbai

Updated on: 29 May,2025 08:57 PM IST  |  Mumbai
mid-day online correspondent |

The concrete curing process, which is a part of the monsoon preparedness planning, will be completed by June 2. Additional Municipal Commissioner (Projects) Abhijit Bangar has directed the departments concerned to remove all the road barricades by June 5 to resume smooth vehicular movement across the city

 BMC claims concretisation work completed on 1,385 roads across Mumbai

The work on 30 roads have been partially completed using mastic asphalt. PIC/BMC

Listen to this article
BMC claims concretisation work completed on 1,385 roads across Mumbai
x
00:00

Under the ongoing initiative to make Mumbai's roads pothole-free, the concrete resurfacing work has been completed on 1,385 roads across the city within the scheduled timeframe, stated the Brihanmumbai Municipal Corporation (BMC). The concrete curing process, which is a part of the monsoon preparedness planning, will be completed by June 2. Additional Municipal Commissioner (Projects) Abhijit Bangar has directed the departments concerned to remove all the road barricades by June 5 to resume smooth vehicular movement across the city.

Bangar conducted an inspection of the ongoing works in the eastern suburbs of Mumbai on Wednesday night. He reviewed the work at Sant Kakkaya Marg in Chembur, Saki Vihar Road, Sicova Industrial Road in Ghatkopar (West), Subhash Nagar Road in Bhandup (West), Surya Nagar Road in Vikhroli (West), Marathon Galaxy Road and Baba Padmasingh Road No 5 in Mulund (West).


Under the cement concretising road project, the BMC said it has completed pavement quality concrete (PQC) works. The work on 30 roads have been partially completed using mastic asphalt. Most roads have been completed end-to-end, while others have been finished junction-to-junction, the civic body informed, adding that the remaining work will be taken up after the monsoon.



On Thursday, Bangar reviewed the status of these projects at the BMC headquarters in Fort.

He stated that the planned road concreting works for this season are nearing completion. While the original deadline for completing the PQC works was May 20, the deadline was extended to May 23, after the city received pre-monsoon showers. This extended deadline was effectively met, he claimed.

With PQC works completed, the final works are currently progressing. These include thermoplastic marking, cat-eyes, directional signs, traffic safety symbols, and junction grids—all of which are scheduled to be completed by June 5. To avoid traffic disruption, these works will be carried out at night.

Given the early onset of the monsoon, road-specific plans should be developed to dispose of leftover materials and debris, Bangar directed the departments concerned. He also said that dedicated teams must be formed, and additional workers should be deployed where needed. He stressed that the removal of debris should be completed within the next two to three days.

In view of the recent heavy rains, Bangar also directed that careful checks be made to ensure stormwater drains are cleaned and free-flowing.

“Water should be flushed through the drains to verify there are no blockages. When connecting newly concreted roads to existing junctions, the junction level must be made uniform using mastic asphalt. He also instructed department offices to submit updated lists of authorised speed breakers, and to begin restoration of these speed breakers,” said Bangar.

Thursday’s meeting was attended by Deputy Commissioner (Infrastructure) Shashank Bhore, Chief Engineer for roads and traffic Girish Nikam, as well as Deputy Chief Engineers, Executive Engineers, Assistant Engineers, and Sub-Engineers.

 

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Did you find this article helpful?

Yes
No

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

mumbai mumbai news BMC news Mumbai roads BMC road projects

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK