Mumbai: On track for 2021 - Snarl-free junction at Kalanagar

With girders launched on pillars late Saturday, MMRDA says 73 per cent of the work on the project is complete

Listen to this article :
The girder being launched on the pillars at Kalanagar on Saturday

The girder being launched on the pillars at Kalanagar on Saturday

What can be seen as an important step towards the completion of the much-awaited Kalanagar flyovers, the MMRDA has successfully launched the girder on the pillars at the junction in Bandra East.

"@MMRDAOfficial achieved another milestone of curved steel girder, 31 mts in length and 40 tons in weight, launching yesterday night in presence of Aaditya Thackeray," the Mumbai Metropolitan Region Development Authority (MMRDA) tweeted on Sunday.

How do you like the new new mid-day.com experience? Share your feedback and help us improve.

Read Next Story
'Why was the previous Maharashtra govt lying about Kanjurmarg?'

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement