Mumbai-Pune E-way trauma centre opening delayed further
Updated On: 02 March, 2015 11:11 AM IST | | Sadaguru Pandit
MSRDC’s much-awaited trauma centre for the Mumbai-Pune Expressway is ready and has even received one bid for operating it, but facilities for maintenance of air ambulances will take six months to get constructed

The Trauma centre constructed by the Maharashtra State Road Development Corporation (MSRDC) off the Mumbai-Pune Expressway will not be available to patients for at least another six months.

The trauma centre at Ozarde village, near Talegaon toll plaza, on the Mumbai-Pune Expressway has received only one bid for operating the facility. Air ambulances cannot yet be brought in because hangar and maintenance facilities will take 6 months to be built