New Diva-Thane rail lines to miss March deadline, too
Updated On: 20 February, 2019 07:15 PM IST | Mumbai | Rajendra B. Aklekar
Certain to miss its March 2019 deadline, the Diva-Thane project across nine kilometres, has been facing several hurdles since its inception. mid-day took a walk along the stretch this week to get the ground report

Levelling work for the fifth and sixth railway lines between Diva and Thane is still underway at some places
Eleven years since work began on the fifth and sixth railway lines between Diva and Thane, the project still awaits completion. Certain to miss its March 2019 deadline, the project across nine kilometres, has been facing several hurdles since its inception. mid-day took a walk along the stretch this week to get the ground report.
Rapid work at stations
Near Diva, on the line towards CSMT, space still needs to be created near the existing level-crossing for the new lines, and rails will have to be aligned to the old tracks. Slightly ahead, work of levelling land next to the mangroves is being done in patches while work on Mumbra station is being done at a rapid pace.