MMRC completes tunneling beneath Mithi River for Mumbai Metro-3
Updated On: 20 August, 2020 02:19 PM IST | Mumbai | Ranjeet Jadhav
Godavari-4 was commissioned on August 21, 2019, from BKC launching shaft and shaped the tunnel with 1,043 RCC rings up to Dharavi

This is the 29th breakthrough on the Colaba-Bandra-SEEPZ Metro-3 corridor
In an important development, the Mumbai Metro Rail Corporation (MMRC) on Wednesday completed a 1.5-km long tunnel beneath the Mithi River. Terratec-made Tunnel Boring Machine (TBM) Godavari-4 completed the upline stretch of 1.5-km from BKC to Dharavi.
Godavari-4 was commissioned on August 21, 2019, from BKC launching shaft and shaped the tunnel with 1,043 RCC rings up to Dharavi. This is the 29th breakthrough on the Colaba-Bandra-SEEPZ Metro-3 corridor.