Eight years on, Nerul RTO still delayed
Updated On: 07 June, 2015 11:45 AM IST | | Ankoor Anvekar
<p>A high-tension wire passing through the plot and payment woes have caused the roadblock</p>

Since 2004, the present Vashi RTO functions from a rented premise at sector 19 inside APMC market
Eight years down the line the proposal of constructing a new regional transport office building at Nerul is still on paper. In 2008 a fresh plan to construct a new Regional Transport Office (RTO) office at Nerul’s sector 13 was sanctioned after the present office at the Agricultural Produce Market Committee (APMC) grain market in Vashi started witnessing space crunch. The new office was to get fully operational by 2013, however the construction work has not yet commenced due of a high tension wire passing through the plot at sector 13.

Since 2004, the present Vashi RTO functions from a rented premise at sector 19 inside APMC market