The 104-year-old bridge, that was deemed unsafe in a report by IIT-B, was pulled down in November 2018. A parallel road bridge was built next to it in 2001.
Listen to this article :

Central Railway dismantles century-old Patri Pul in Kalyan, after IIT-B safety audit deems it unsafe, on Sunday. Pics/Sameer Markande
The girders of Kalyan's Patri Pul finally arrived from Global Steel Company, Hyderabad about 700 km away and now work on the bridge is likely to be speeded up.
There are plans to triple the bridge capacity and work is expected to be complete before this monsoon. The total cost of the bridge reconstruction is Rs778.11 crore.