Home / Mumbai / Mumbai News / Article /
MahaRERA allows Thane homebuyers to exit luxury housing project after possession delayed by five years
Updated On: 19 November, 2026 08:23 AM IST | Mumbai | Vinod Kumar Menon
Rejecting force majeure and ‘allottees core committee’ settlement defences, regulator directs Jaykali Developers to refund two homebuyers with interest within 60 days over stalled project

Representation pic/iStock
In two identical orders dated November 6, 2026, MahaRERA Member II Ravindra Deshpande ruled in favour of two sets of homebuyers who sought to exit Jaykali Developers Private Limited, a subsidiary of SPRE (Shapoorji Pallonji Real Estate)'s luxury slum rehabilitation project, Omega - Northern Lights, in Thane West, over delayed possession.
The authority allowed the buyers to withdraw from the project and directed the developer to refund the amounts paid, along with interest. Both flats were promised for possession by March 2024, but the developer subsequently secured a project extension until March 2029.