Updated On: 10 January, 2018 05:32 PM IST | Mumbai | Vinod Kumar Menon
The authorities are upset that numerous builders in Mumbai are using Intent of Disapproval as permission for construction; says Commencement Certificate is the stage after obtaining IOD


The reaction comes after an order passed by MahaRERA on January 2
The Maharashtra Real Estate Regulatory Authority (MahaRERA) has expressed its displeasure over many builders in Mumbai using Intent of Disapproval (IOD) as permission to proceed with construction. It cannot be equated with Commencement Certificate (CC), which is the stage after obtaining IOD, clarified a Member and Adjudicating officer, MahaRERA. The officer has directed RERA authorities to make a provision online for mandatory uploading of CCs, which are not being uploaded due to the lack of such a provision currently.