Mumbai: After SC relief, BMC rushes to resume work on coastal road
Updated On: 18 December, 2019 07:05 AM IST | Mumbai | Prajakta Kasale
While BMC seeks to waste no more time, activists slam SC directive, say it will cause loss of biodiversity
Listen to this article :

The BMC has completed 6.25 per cent of work on the coastal road. Pic/ Bipin Kokate
After the Supreme Court on Tuesday stayed a Bombay High Court order directing the civic body to stop work on the coastal road project, the Brihanmumbai Municipal Corporation (BMC) is all set to resume construction on Wednesday.
Official intimation has been sent to both contractors. The civic body intends to complete as much work as possible before April, the next date of the Supreme Court (SC) hearing. Only 6.25 per cent work has been done on the project so far.