Home > Mumbai > Mumbai News > Article > 300 km of viaducts completed for Mumbai Ahmedabad Bullet train project

300 km of viaducts completed for Mumbai-Ahmedabad Bullet train project

Updated on: 20 May,2025 03:06 PM IST  |  Mumbai
mid-day online correspondent |

The project has supported use of indigenously designed and manufactured equipment such as Straddle Carriers, Launching Gantries, Bridge Gantries, and Girder Transporters for construction. This marks a first for Indian infrastructure, showcasing India's growing capabilities in high-speed rail technology with the support of the Japanese government

300 km of viaducts completed for Mumbai-Ahmedabad Bullet train project

The adoption of the Full Span Launching Method has significantly accelerated construction, as full-span girder erection is up to ten (10) times faster than conventional segmental methods

Listen to this article
300 km of viaducts completed for Mumbai-Ahmedabad Bullet train project
x
00:00

India’s first Bullet Train corridor between Mumbai and Ahmedabad has reached a significant construction milestone with the successful completion of 300 km of viaducts. This achievement was marked by the launching of a 40 m long full-span box girder near Surat, Gujarat, according to the National High Speed Rail Corporation Limited (NHSRCL) statement.

Out of 300 km of superstructure, 257.4 km is constructed through Full Span Launching Method (FSLM) including 14 river bridges, 37.8 km through Span by Span (SBS), 0.9 km steel bridges (10 spans ranging from 60 to 130 m in 7 bridges), 1.2 km PSC bridges (20 spans ranging from 40 to 80 m in 5 bridges) and 2.7 km in station building.


For constructing 257.4 km of viaduct through FSLM and 37.8 km of viaduct through SBS, 6455 & 925 spans of 40 m each, respectively, were used.


The project has supported the use of indigenously designed and manufactured equipment such as straddle carriers, launching gantries, bridge gantries, and girder transporters for construction. This marks a first for Indian infrastructure, showcasing India's growing capabilities in high-speed rail technology with the support of the Japanese government.

The adoption of the full span launching method has significantly accelerated construction, as full-span girder erection is up to ten (10) times faster than conventional segmental methods. Each full-span box girder weighs 970 metric tons. Segmental girders are used selectively in locations where full-span installation is not feasible.

To facilitate construction, 27 dedicated casting yards were established along the corridor. Steel bridges are fabricated in seven workshops spread all across the country, three in Gujarat, one each in Uttar Pradesh, Tamil Nadu, Maharashtra and West Bengal truly exemplifying the spirit of unity of our country.

More than 3 lakh noise barriers have been installed along the viaducts to mitigate noise during operations.

In addition to the viaducts, the project has also completed 383 km of pier work, 401 km of foundation work and 326 km of girder casting.

The thematic Bullet Train stations are rapidly taking shape. These stations will be integrated with the rail and road-based transport system to provide seamless travel to passengers. The stations will be equipped with state-of-the-art passenger amenities.

Track works over viaducts have also started and around 157 track km of RC track bed construction has been achieved so far in Gujarat.

The rolling stock depots with modern infrastructure are also getting ready in Maharashtra and Gujarat.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Did you find this article helpful?

Yes
No

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK