Home / Mumbai / Mumbai News / Article / Mumbai: Army personnel bridge Ambivli station gap in one hour flat

Mumbai: Army personnel bridge Ambivli station gap in one hour flat

Working in perfect sync, Army personnel lift and place the final girders of the Bailey bridge at Ambivli stn

  • WhatsAppBookmarkBookmark
Listen to this article :

Ambivli station

With cries of Jai Hind and salutes, the Bombay Sappers Engineering Team from the Indian Army lifted and placed the final girders of the assembled Bailey bridge at Ambivli station in about 20 minutes and fixed them on the foundations, completing the initial launch procedure in one hour flat, as the railways stopped all trains on the section for three hours for the work. The day’s work was completed in four and a half hours. The 3.759-m wide foot overbridge will open to the public by January 26.