BMC completed demolition in just 13,211 of 2.14 lakh illegal construction complaints
Updated On: 06 November, 2026 11:20 AM IST | Mumbai | Ritika Gondhalekar
An RTI has revealed that the BMC received 2,14,917 complaints of illegal constructions through its RETMS portal between March 2016 and October 2026. While 1,16,228 were marked as duplicates, demolition was completed in only 13,211 cases, accounting for around 6.15 per cent of total complaints

Representational image. File pic
Over 10 years, 2,14,917 complaints were registered on the RETMS portal; 1,16,228 marked as duplicates, leaving 98,689 actual complaints. Demolition completed in just 13,211 cases. An RTI has exposed the shocking state of BMC's functioning.
While the Maharashtra government dreams of transforming Mumbai into Shanghai, shocking revelations through the Right to Information (RTI) Act suggest that the functioning of the Brihanmumbai Municipal Corporation (BMC) is undermining this vision.