Mumbai civic body seeks bigger role for corporators in Rs 17,000-crore road concreting project

Updated on: 13 February,2026 09:53 AM IST  |  Mumbai
Eeshanpriya MS | mailbag@mid-day.com

The Brihanmumbai Municipal Corporation has directed that all excavation and concreting work be completed before the rainy season. Engineers must remain present on-site to ensure strict quality control across 2,121 roads

Mumbai civic body seeks bigger role for corporators in Rs 17,000-crore road concreting project

The cost of the project that seeks to make Mumbai free of potholes is Rs 17,000 crore. Representation Pic/Shadab Khan

Listen to this article
Mumbai civic body seeks bigger role for corporators in Rs 17,000-crore road concreting project
x
00:00

With 90 days to go before the onset of the monsoon, the BMC administration has sought a larger role from the newly elected representatives in its ongoing Rs 17,000 crore road concreting work. In an administrative review meeting conducted by Municipal Commissioner Bhushan Gagrani on Wednesday, following the elections of Mumbai’s mayor and her deputy, the administration has been directed to keep elected representatives informed of the status of all ongoing road work and to take routine feedback back from them. 

“The feedback received from citizens can be easily communicated to the administration through elected representatives, adding an extra layer of quality checks,” an official said. The BMC has also said all work on all excavated roads will be completed before the monsoon season, to avoid exposing unfinished sections to the rain. According to the civic body, the incidence of potholes due to rain on concrete roads is minimal, resulting in significant savings in maintenance and upkeep costs.


Top directives
>> Ensure work started from October 1, 2025, is completed by the rainy season
>> Complete all excavation work before the monsoon
>> It is mandatory for engineers to be present at concreting work sites
>> Quality work includes ensuring that all conditions are strictly met at every level



Status of work
Phase 1
Number of roads: 700
Completion: 77%

Phase 2
Number of roads: 1420
Completion: 52%
Combined length of roads
concreted so far: 410 km

Project details
Total cost: Rs 17,000 cr
Total no of r ads: 2121
Total length of roads: 696.85 km
Timeline of project: January 2023 to 2027
Percentage of work completed: 63 per cent

Top 4 wards where work has been completed

R Central
Completed: 131
In progress:  44
Pending: 10

P North
Completed: 102
In progress: 35
Pending: 8
 
P South
Completed: 81
In progress: 40
Pending: 16
 
K West
Completed: 78
In progress: 54
Pending: 15

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Did you find this article helpful?

Yes
No

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

mumbai monsoon monsoon season mumbai rains heavy rains BMC road projects Road construction mumbai mumbai news