Mumbai: Borivali-Virar 5th, 6th lines project hits 30 per cent progress; completion targeted for 2029

The project, sanctioned at a cost of Rs 2,184 crore, is a major capacity augmentation project on the Western Railway suburban corridor. The 26-km stretch between Borivali and Virar is being expanded to segregate long-distance trains from suburban local services

  • WhatsAppBookmarkBookmark
Listen to this article :
 Relocation of railway structures at Dahisar, Mira Road, Bhayander, Naigaon, Nalasopara, and Vasai Road is either complete or at an advanced stage. FILE PIC

Relocation of railway structures at Dahisar, Mira Road, Bhayander, Naigaon, Nalasopara, and Vasai Road is either complete or at an advanced stage. FILE PIC

The Borivali-Virar 5th and 6th Lines Project under the Mumbai Urban Transport Project-IIIA (MUTP-IIIA) has achieved 30 per cent physical progress and is targeted for completion in 2029, the Mumbai Railway Vikas Corporation Ltd (MRVC) said on Sunday.

The project, sanctioned at a cost of Rs 2,184 crore, is a major capacity augmentation project on the Western Railway suburban corridor.

Hotproperty Ad Banner
Hotproperty Ad Banner
Read Next Story
Mumbai: Airoli-Kalwa elevated suburban corridor achieves 45 per cent progress amid land delays

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All