Mumbai: CAG finds serious irregularities in CIDCO projects

CAG reviews infrastructure projects, including three major ones, accuses CIDCO of not adhering to plan

Listen to this article :
Incorporated in 1970 as a state-owned company, the CIDCO undertakes developmental works, provides social and physical infrastructure, mainly in Navi Mumbai and adjoining areas. File pic

Incorporated in 1970 as a state-owned company, the CIDCO undertakes developmental works, provides social and physical infrastructure, mainly in Navi Mumbai and adjoining areas. File pic

The Comptroller and Auditor General (CAG) in its 2018 report has cited serious strictures against the City and Industrial Development Corporation (CIDCO), the infrastructure planning and executing agency for Navi Mumbai. The report was tabled by Finance Minister Ajit Pawar on Wednesday.

In its report, CAG has accused CIDCO of inadequate planning, not carrying out proper surveys and feasibility study, failing to make realistic estimates prior to tendering the works and giving works to inexperienced contractors, causing huge losses.

How do you like the new new mid-day.com experience? Share your feedback and help us improve.

Read Next Story
Mumbai crime: Convicted matka king murderer held for extortion

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement