Mid-Day was the first to report that the railways and MMRDA were carrying out this rare project

Central Railway's first readymade foot overbridge (FOB) installed
The Central Railway's (CR) first readymade foot overbridge (FOB) was installed on Thursday night between Sion and Kurla stations. Generally, the FOBs are constructed by fitting multiple blocks on the site. Mid-Day was the first to report that the railways and Mumbai Metropolitan Region Development Authority (MMRDA) were carrying out this rare project.
Watch the video of Central Railway's first readymade bridge:
In a rare move, the #CentralRailway and MMRDA create Central Railway's first readymade bridge in just one go! @Central_Railway @rajtoday @PiyushGoyalOffc @PiyushGoyal @MMRDAOfficial pic.twitter.com/sVF19tnCQK
— mid-day (@mid_day) October 18, 2019
"The FOB was built meticulously to the exact measure of the lines and placed with the help of heavy road cranes," a senior railway official, who did not wish to be named, said.