Home / Mumbai / Mumbai News / Article / Central Railway launches 500-tonne girder for Mumbai's Sion ROB reconstruction

Central Railway launches 500-tonne girder for Mumbai's Sion ROB reconstruction

The girder was launched during a night traffic block between Matunga and Kurla stations as part of the Chhatrapati Shivaji Maharaj Terminus (CSMT), Kurla fifth and sixth line project, one of Mumbai's key railway capacity enhancement initiatives

  • WhatsAppBookmarkBookmark
Listen to this article :
With the steel girder now in place, construction activities such as deck slab work and road surfacing. Pic/ Central Railway

With the steel girder now in place, construction activities such as deck slab work and road surfacing. Pic/ Central Railway

Central Railway has successfully launched a 500-tonne semi-through steel girder for the reconstruction of the Sion Road Over Bridge (ROB), marking a major milestone in the long-pending infrastructure project.

The girder was launched during a night traffic block between Matunga and Kurla stations as part of the Chhatrapati Shivaji Maharaj Terminus (CSMT), Kurla fifth and sixth line project, one of Mumbai's key railway capacity enhancement initiatives.

Hotproperty Ad Banner
Hotproperty Ad Banner
Read Next Story
Maharashtra weather update: Rain hits parts of state as thunderstorms grip Mumbai, Pune, and Konkan belt

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All