Mumbai: Central Railway main line to be free of level crossings soon

Work on three bridges, stuck for decades, may be completed this year in lockdown

  • WhatsAppBookmarkBookmark
Listen to this article :

Mission Zero LC Gates on Central Railway, Mumbai's main line, may finally become a reality in one year. While mid-day had reported about the status of the Kalwa gate that is likely to shut next year, two more of those troublesome level crossing gates at Diva and Ambivli are all set to go as work gathers momentum in the lockdown.

The three level crossing (LC) gates at Kalwa, Diva and Ambivli put together, brought to a standstill 55 trains over 5 minutes every single day as they opened every 15-20 minutes, collapsing the entire timetable. Road bridges over these gates have been pending for decades due to a number of complications by local municipal corporations.

Read Next Story
Mumbai: TB hospital superintendent sacked over body in toilet

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All