Home > Mumbai > Mumbai News > Article > Mid Day Impact Charni Road FOB gets staircase after long delay final phase still pending

Mid-Day Impact | Charni Road FOB gets staircase after long delay; final phase still pending

Updated on: 01 July,2025 02:16 PM IST  |  Mumbai
Rajendra B. Aklekar | rajendra.aklekar@mid-day.com

After mid-day's relentless coverage, Charni Road's hanging FOB gets staircase, residents cheer, Rlys promises mid-July opening

Mid-Day Impact | Charni Road FOB gets staircase after long delay; final phase still pending

The bridge now connects Pandit Paluskar Chowk on Charni Road East to the main road near Chowpatty. Pic/Ashish Raje

Listen to this article
Mid-Day Impact | Charni Road FOB gets staircase after long delay; final phase still pending
x
00:00

The long-pending Charni Road foot overbridge (FOB) has finally received its staircase, giving the ‘hanging’ bridge a proper landing. mid-day has consistently highlighted the issue over the past few years, and the construction is now in its final stages. This is the first phase of the project. The second important key phase of the bridge crossing the main sea-facing road is still pending as the BMC is yet to figure out about it.

The incomplete bridge that had no staircase. Pic/Sayyed Sameer Abedi
The incomplete bridge that had no staircase. Pic/Sayyed Sameer Abedi


Relieved residents in the area have expressed their gratitude to mid-day and called for the early opening of the bridge. For years, the FOB remained suspended without stairs due to a land dispute between the Brihanmumbai Municipal Corporation (BMC) and Western Railway.



The bridge connects Pandit Paluskar Chowk on Charni Road East to the main road near Chowpatty, but had remained inaccessible due to the missing west-side staircase. Many commuters using the nearby railway FOB to cross from east to west were fined for using it without a valid train ticket.

“There was a functional foot overbridge many years ago. Authorities demolished it to upgrade the structure, but the new bridge was left hanging without stairs on the west side, turning it into a useless balcony. Now, one part has opened and the other one is awaited, which is deadlier,” said a resident.

The long-pending Charni Road foot overbridge (FOB) has finally received its staircase. Pic/Ashish Raje
The long-pending Charni Road foot overbridge (FOB) has finally received its staircase. Pic/Ashish Raje

“We thank mid-day for continuously raising this issue. The bridge is ready but hasn’t been opened for some strange reason. When I called the officer, he blamed the delay on the rain. BMC has done absolutely nothing regarding their part of the bridge. So people will have no option but to continue crossing the Marine Drive road till the bridge is completed,” said local activist Jeetendra Ghadge. Western Railway officials have assured that the bridge will be open to the public before July 15.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Did you find this article helpful?

Yes
No

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

charni road brihanmumbai municipal corporation indian railways mumbai railways western railway mumbai news mumbai

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK