Home / Mumbai / Mumbai News / Article / Mumbai Coastal Road is 17 per cent complete: BMC chief Chahal

Mumbai Coastal Road is 17 per cent complete: BMC chief Chahal

A highlight of the project will be a 400-metre long and 39.60 feet diameter tunnel boring machine (TBM), which has been fully assembled.

  • WhatsAppBookmarkBookmark
Listen to this article :
Coastal Road Project site at Napean Sea Road | Pic: Sayyed Sameer Abedi

Coastal Road Project site at Napean Sea Road | Pic: Sayyed Sameer Abedi

The ambitious 8-lane Mumbai Coastal Road project is now 17 per cent complete on the southern side from Marine Drive to Worli and the sector is expected to be operational by July 2023, BMC Municipal Commissioner I.S. Chahal said here on Monday.

"Substantial work has been done in the past couple of months spending Rs 1,281-crore till November, and about 17 percent work of the project is completed," Chahal told IANS.

Read Next Story
Cyber Cell files FIR in case of Urmila Matondkar's hacked Instagram

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All