Mumbai: Construction of Delisle Road bridge inches ahead
Updated On: 23 July, 2020 06:01 AM IST | Mumbai | Rajendra B Aklekar
The Delisle Road bridge was shut for traffic in July 2018, hugely impacting office-goers working in the nearby business district of Lower Parel. The bridge, a crucial city link, was then demolished following an audit by IIT-B

With the completion of the raft foundation on the west side of the bridge, the entire foundation has been built
The Western Railway on Tuesday announced that it had achieved a major milestone in the much-awaited Delisle Road, Lower Parel bridge construction on Sunday, by completing its foundations.
Given the complexity of the project, the bridge will, however, be ready for citizens only by March 22, 2022. While the east side foundations were completed in May 2020, the making of steel girders for the bridge has begun at Kota in Rajasthan.