Updated On: 02 June, 2015 06:56 AM IST | | Shashank Rao
<p>During inspection, authorities have identified spots between CST and Thane where there is insufficient space between overhead wires and bridges, which is posing a problem for conversion to 25,000-volt AC</p>
Listen to this article :

Central Railway (CR) could face a tough challenge in completing the power conversion from 1,500-volt DC to 25,000-volt AC. During inspection, authorities have found nine spots where trains operating on the new power system could face the barrier of insufficient height between the tracks and overhead lines.
All these spots are either under road over bridges (ROBs) or foot over bridges (FOBs). Representation pic