Mumbai: Kurla elevated station construction races ahead
Updated On: 14 March, 2020 07:45 AM IST | Mumbai | Rajendra B Aklekar
mid-day was the first to report the Rs 125 crore elevated harbour line station in October 2017

Four composite girders were launched one after the other at the site of Kurla elevated station
In swift developments on the Kurla elevated station, the Central Railway, in the past two weeks launched as many as four composite girders one after the other at the site. The project is scheduled to be completed within the next two years.
mid-day was the first to report the Rs 125 crore elevated harbour line station in October 2017. When ready, the terminus will aid CR in reviving services of Kurla-originating trains to Navi Mumbai after two decades. mid-day had published the designs of the bridge on September 25, 2019, stating that the plans had been locked along the lines of the Parel mid-terminus with a three platform plan.