Dahisar-Bhayandar Link Road: Mumbai civic body targets December 2028 completion; girder-launching from October
Updated On: 12 September, 2026 09:45 PM IST | Mumbai | mid-day online correspondent
The DBLR is part of the Mumbai Coastal Road (North), an ambitious BMC infrastructure project aimed at easing traffic congestion in MMR and providing smoother connectivity. The larger project, including interchanges and link roads, spans around 60 km

Additional Municipal Commissioner (Projects) Abhijit Bangar inspected the project site at the Bhayandar Interchange in the Mira-Bhayandar Municipal Corporation area. PIC/BY SPECIAL ARRANGEMENT
Work on the Dahisar-Bhayandar Link Road (DBLR), a key infrastructure project aimed at improving connectivity between Mumbai and the Mira-Bhayandar region, is progressing, with the Brihanmumbai Municipal Corporation (BMC) targeting completion by December 2028.
Additional Municipal Commissioner (Projects) Abhijit Bangar inspected the project site at the Bhayandar Interchange in the Mira-Bhayandar Municipal Corporation area and reviewed the ongoing works. He also issued directions regarding the project’s implementation and safety measures.