Good news for Mumbai! Rajnoli flyover work nears completion

According to the latest reports by MMRDA, 85 percent development Rajnoli flyover work has been completed and the right side of the flyover is expected to be opened to traffic very soon

Listen to this article :
The six crucial 50-meter long steel girders have been installed at the Rajnoli Junction

The six crucial 50-meter long steel girders have been installed at the Rajnoli Junction

If all goes to plan, motorists who have been facing traffic issues will no longer have to waste time at the Rajnoli Junction on the Kalyan-Bhiwandi Road as the Mumbai Metropolitan Region Development Authority (MMRDA) has launched six crucial 50-meter long steel girders, weighing 50 Metric Tonnes each.

In a press release issued to the media, it has been stated that because of this development 85 percent of the right side of Rajnoli flyover work has been completed and the right side of the flyover is expected to be opened to traffic very soon. The girders were launched during the early hours of July 3 and 4.

How do you like the new new mid-day.com experience? Share your feedback and help us improve.

Read Next Story
Out of the box

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement