Mumbai Trans Harbour Link: 76 pc work completed, aim to complete work by September 2023, says MMRDA

Out of 6 interchanges of the MTHL project at Sewri, work on the C-2, ramp has been completed up to subbase and also work on the 4 km of spread up to the deck slab of the original bridge from the access road, has been completed

Listen to this article :
Aaditya Thackeray inspects MTHL project with Metropolitan Commissioner of MMRDA, SVR Srinivas. Pic/MMRDA

Aaditya Thackeray inspects MTHL project with Metropolitan Commissioner of MMRDA, SVR Srinivas. Pic/MMRDA

Around 76 per cent of the Mumbai Trans Harbour Link Project (MTHL) project at Sewri has been completed and MMRDA is planning to finish the work by the end of September 2023.

Out of 6 interchanges of the MTHL project at Sewri, work on the C-2, ramp has been completed up to subbase and also work on the 4 km of spread up to the deck slab of the original bridge from the access road, has been completed.

How do you like the new new mid-day.com experience? Share your feedback and help us improve.

Read Next Story
INS Vikrant case: Kirit Somaiya deposited money with BJP, claims Sanjay Raut

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement