Home / Mumbai / Mumbai News / Article /
Mumbai: Western Railway opens new FOB for commuters at Bandra station
Updated On: 29 September, 2020 09:00 AM IST | Mumbai | Rajendra B Aklekar
This Foot Over Bridge has been constructed at an approximate cost of Rs 5 crore

The new FOB at Bandra station has been constructed at an approximate cost of Rs 5 crore
The Western Railway on Monday commissioned a new six-metre wide Foot Over Bridge (Middle) at Bandra station. The work on this new FOB was completed on September 28 and was opened for commuters on the same day. The new FOB connects all platforms of the station, including east to west through MCGM skywalk on the west side.
According to Sumit Thakur, chief public relations officer of Western Railway, the new FOB is 80 meters long and 6 meters wide. This FOB has been constructed at an approximate cost of Rs 5 crore. It is constructed at the place of Old Middle Truss FOB, which was declared unsafe in the audit report of the survey conducted by IIT-Bombay.