Concrete roads deepen BEST-BMC standoff on power repairs in Mumbai
Updated On: 19 May, 2026 07:44 AM IST | Mumbai | Rajendra B. Aklekar
BEST says Mumbai’s road concreting drive is slowing power fault repairs, with digging permissions delaying restoration work across the city

BEST staff lay and repair underground power cables amid ongoing restoration work
Mumbai’s ongoing road concreting drive is now affecting power restoration timelines, with BEST officials claiming delays in permissions to dig newly built roads are slowing down repairs to underground cable faults.
According to BEST officials, complaints related to power supply issues have risen sharply over the past year, even as restoration teams struggle to access underground utility lines buried beneath concreted roads.