Mumbai’s Elevated Eastern Freeway Extension moves towards segment launching phase

The Rs 2682 crore elevated corridor moves into its next phase, with 1632 precast segments to be erected span by span

  • WhatsAppBookmarkBookmark
Listen to this article :
The ongoing work on the freeway. Pic/Malhar Pawar

The ongoing work on the freeway. Pic/Malhar Pawar

The MMRDA has completed 165 of the 395 planned piers for Mumbai’s 13.9-km Elevated Eastern Freeway Extension (EFE), with work now moving towards the next major phase — launching precast segments over the completed piers.

The segment launcher’s two main trusses were installed in July. After the monsoon, the launcher will be used to erect 1,632 precast segments, each weighing around 90 tonnes, span by span to form the elevated viaduct.

Read Next Story
Mumbai: Khar police arrest man after 21 years for allegedly evading theft case proceedings

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All