Navi Mumbai: Tribunal directs Ulwe builder to hand over flats to 19 buyers within 30 days
Updated On: 07 November, 2026 07:51 AM IST | Mumbai | Vinod Kumar Menon
In a Diwali relief for 19 Ulwe flat buyers, the Maharashtra Real Estate Appellate Tribunal has directed Prathmesh Construction to hand over possession within 30 days of receiving outstanding dues. The developer has disputed the claims and plans to challenge the order before the Bombay High Court

Prathmesh Harmony Cooperative Hsg Society in Ulwe, where 19 flat buyers have secured interim relief from Maharashtra Real Estate Appellate Tribunal. Pic/special arrangement
For 19 flat buyers in Ulwe, Navi Mumbai, this Diwali brings the prospect of finally entering homes they paid for nearly a decade ago. The Maharashtra Real Estate Appellate Tribunal has directed M/s Prathmesh Construction to hand over possession within 30 days of receiving the buyers' outstanding dues.
In its November 4, 2026 order, a bench comprising Chairperson Justice S S Shinde and Member (A) Shrikant M Deshpande partly allowed all 19 possession applications and restrained the developer from creating third-party rights over the flats.