Pending for 3 years, rail bridge re-girding completed in 14 hours

Re-girding of a bridge on the Churchgate-bound fast line in the Bandra-Mahim section, which would have otherwise required cancellation of at least 250 local train services, was completed within 14 hours on April 30.

  • WhatsAppBookmarkBookmark
Listen to this article :
Railways decided to utilise the lockdown period to carry out re-girding work

Railways decided to utilise the lockdown period to carry out re-girding work

The COVID-19 lockdown is turning out to be a blessing in disguise for all of Mumbai's pending rail work. Re-girding of a bridge on the Churchgate-bound fast line in the Bandra-Mahim section, which would have otherwise required cancellation of at least 250 local train services, was completed within 14 hours on April 30.

The steel bridge, which spans 9.15 metres and has seven cross-girders of length 5.8 metres is located on the Mithi River. The steel girders needed to be immediately replaced as they had got corroded.