Mumbai: 12 bullet points to make high-speed train a reality
Updated On: 18 October, 2018 07:47 AM IST | Mumbai | Rajendra B. Aklekar
Project officials are now looking to follow the slow-moving but assured land-acquisition model of the Nagpur-Mumbai Expressway

Setting up a new medical unit at Viratan Khurd was one of the ways the bullet train team had tried to win the villagers over. File pic
Palghar seems to have hit the brakes on the bullet train project yet again, with political parties allegedly turning villagers against the project. So far, the authorities have spared neither money nor effort in their attempts to acquire land, but it seems they have not tried the most basic approach: directly approaching land owners and clearing their doubts.
The Palghar collector's office has now issued a 12-point letter to bullet train authorities to take a more direct and personal approach while wooing the land owners, like the Maharashtra State Road Development Corporation (MSRDC) had done for the Mumbai-Nagpur Samruddhi Expressway.