Home / Mumbai / Mumbai News / Article /
Mumbai-Nanded Vande Bharat train delayed after OHE fault near Kasara
Updated On: 27 July, 2026 08:22 PM IST | Mumbai | Rajendra B. Aklekar
According to a Central Railway spokesperson, railway staff immediately attended to the defective OHE insulator and carried out the necessary repairs on priority
Listen to this article :

Officials said that the repair work was completed without any further operational issues. Representational Pic/File
The Mumbai-Nanded Vande Bharat Express was delayed on Monday after an overhead equipment (OHE) insulator developed a fault in the Kasara-Igatpuri ghat section, officials said.
Railway officials said the issue was resolved quickly, and the train resumed its journey after a delay of around 32 minutes.