Home / News / India News / Article / Bombay HC allows Metro debris removal work post midnight for 3 days

Bombay HC allows Metro debris removal work post midnight for 3 days

The Bombay High Court today allowed the Mumbai Metro Rail Corporation Limited (MMRCL) to carry out work of removal of debris from construction sites of the Metro III project on a temporary basis for three days, post midnight

  • WhatsAppBookmarkBookmark
Listen to this article :

The Bombay High Court today allowed the Mumbai Metro Rail Corporation Limited (MMRCL) to carry out work of removal of debris from construction sites of the Metro III project on a temporary basis for three days, post midnight.

The order was passed by a division bench of Chief Justice Manjula Chellur and Justice M S Sonak while hearing a petition filed by advocate Robin Jaisinghani that the construction activity for the project was resulting in noise pollution in the areas concerned.

Read Next Story
HC asks woman cop to move MAT for leave to undergo sex-change